Arch bridge over the Seidewitztal in Saxony/ Germany. Part of the Bundesautobahn A17 over the S176. Doka delivers the formwork for the arch form traveler from Wito (Austria). |
|
|
 |
|
Bridge type:
|
Arch bridge, seperated superstructures on spandrel columns
|
|
Location:
|
Saxony/ Germany
|
|
Total construction time:
|
Approx. years (2004-2006)
|
|
Construction time arch:
|
Approx. 8 months (for each arch)
|
|
 |
|
Total length of bridge:
|
568 m
|
|
Span of arch:
|
154 m
|
|
Elevation of arch crown:
|
55 m
|
|
Construction method:
|
Cantilver construction with auxiliary staying
|
|
Cross section:
|
Arch: Solid
|
|
|
Superstructure: Composite deck
|
|
 |
-
Spandrel columns with Doka Climbing Formwork MF 240
-
Main steel girders of composite deck were incrementally launched
-
Superstructure with Doka composite forming carriage
|
|
Ed. Züblin AG (Germany)
|
 |
|
 |
 |