The Friedrich-Ebert-Bridge / Mannheim (undercurrent) is situated directly adjacent and paralell to the existing Friedrich-Ebert-Bridge / (uppercurrent) over the river Neckar.
|
|
|
 |
|
Bridge type:
|
Slab-and-beam bridge
|
|
Location:
|
Germany
|
|
Total construction time:
|
2006
|
|
 |
|
Total length of bridge:
|
198 m
|
|
Number of spans:
|
3
|
|
Span maximum:
|
86 m
|
|
Piers:
|
2 Piers
|
|
Construction method:
|
Cantilever construction method
|
|
Cross section:
|
slabs-and-beams (slab with 2 beams)
|
|
 |
-
Only the middle span was constructed using cantilever construction method.
-
The formwork for the beams, deck and cantilever slabs were produced in Doka ready-to-use service in Maisach.
|
Dywidag Bau GmbH (Deutschland)
|
 |
|
 |
 |