| Overslung composite forming carriage |
|
|
|
 |
|
Type of bridge:
|
Composite Bridge
|
|
Location:
|
BAB A 38, Göttingen/Halle, Germany
|
|
Total construction time:
|
~ 30 months
|
|
|
|
|
|
|
|
 |
|
Length:
|
1115 m
|
|
Height:
|
~ 49 m
|
|
Method:
|
back-step technique
|
|
Step lenght:
|
up to 22,5 m
|
|
Steps:
|
53
|
|
|
|
|
 |
|
Formwork traveler, back-step technique, weekly cycle, modular system
|
 |