Project information
Bridgewater Place
Project data
Type of building: Offices, residences and hotel
Location: Leeds, UK
Start of construction: October, 2004
Total construction time: ~ 18 months
Construction time cores: ~ 9 months
Building data
Height: ~ 107 m
Method: Core ahead
Step height: Regular step height 2,90 m
Floors: 30
Steps: 33
Contractor
Site management: Bovis Lend Lease
Additional infos
  • One step per week
Formwork design
Contact Doka UK:
  E-Mail: Mr. Richard Seers (Technical Manager)
Contact Self-climbing Systems Expertise Centre Amstetten:
  E-Mail: Mr. Hannes Stolzlechner (Project Manager Amstetten)
More on this topic
Project information
Pics
Plans
Products in use
Doka climbing formwork GCS
Doka automatic climbing formwork SKE
More on this topic
Doka raises safety levels at Leed´s tallest tower
Find more on www.skyscrapers.com