Project information
Paradise Street - Site 12
Project data
Type of building: High-rise building
Location: Liverpool, UK
Start of construction: October, 2006
Total construction time: ~ 9 months
Construction time cores: ~ 6 months
Building data
Height: ~ 66 m (1 core)
~ 48 m (3 cores)
Method: Cores ahead
Step heights: Regular step height 3,0 m (1 core)
Regular step height 4,5 m (3 cores)
Floors: 22 (1 core)
16 (3 cores)
Steps: 22 (1 core)
11 (3 cores)
Additional infos
  • 1-2 weeks per step
  • 4 cores
  • 75 mm wall thickness change
  • Climbing formwork with windshield
Contractor
Laing O'Rourke
Formwork design
Organisation in country: Doka UK
  E-Mail: Mr. Simon Dowd (Sales Representative)
  E-Mail: Mr. Richard Seers (Technical Manager))
Contact Engineering Amstetten
  E-Mail: Mr. Michael Eder (Projectmanager Amstetten)