Type of building:
|
High-rise building
|
|
Location:
|
Liverpool, UK
|
|
Start of construction:
|
October, 2006
|
|
Total construction time:
|
~ 9 months
|
|
Construction time cores:
|
~ 6 months
|
|
 |
|
Height:
|
~ 66 m (1 core)
|
|
|
~ 48 m (3 cores)
|
|
Method:
|
Cores ahead
|
|
Step heights:
|
Regular step height 3,0 m (1 core)
|
|
|
Regular step height 4,5 m (3 cores)
|
|
Floors:
|
22 (1 core)
|
|
|
16 (3 cores)
|
|
Steps:
|
22 (1 core)
|
|
|
11 (3 cores)
|
|
 |
-
1-2 weeks per step
-
4 cores
-
75 mm wall thickness change
-
Climbing formwork with windshield
|
|
Laing O'Rourke
|
 |
|
Organisation in country: Doka UK
|
 |
|
Contact Engineering Amstetten
|
 |
|
 |
 |