Type of building:
|
High-rise building
|
|
Location:
|
London, UK
|
|
Start of construction:
|
October, 2005
|
|
Total construction time:
|
~ 14 months
|
|
Construction time facade:
|
~ 13 months
|
|
 |
|
Height:
|
~ 100 m
|
|
Method:
|
Cores ahead
|
|
Step height:
|
Regular step height 3,0 m
|
|
Floors:
|
32
|
|
 |
-
1-2 weeks per step
-
In the upper part of the building the platforms are also used to set up the formwork
|
|
PC Harrington Ltd.
|
 |
|
Organisation in country: Doka UK
|
 |
|
Contact Engineering Amstetten
|
 |
|
 |
 |