Project information
Rhine Bridge Wesel
Project data
Type of building: Pylon
Location: Wesel / Deutschland
Start of construction: Mai, 2005
Total construction time: ~45 months
Construction time pylon: ~12 months
Building data
Height: ~113 m without base / ~130 m with base
Method: Conventional
Step height: regular step height 4,88m/5,00m
Steps 26 (without base)
Additional info
  • 3-4 days cycle
  • Pylon in fair-faced concrete
  • Shaped like an upside-down letter Y
  • Variable cross-sections of the tower legs
  • Very steeply – 15.84° – inclined tower legs
  • The two tower legs were braced against one another.
    This presented a real challenge for the climbing formwork
Contractor
HERMANN KIRCHNER - Hoch- und Ingenieurbau GmbH - Bad Hersfeld
www.kirchner.de
Contact: Lars Hassenpflug (Site manager)
Formwork design
Organisation in Country: Doka Germany
  E-Mail: Hr. Mario Biniok (Sales Representative)
  E-Mail: Hr. Benedikt Willecke (Technical Manager)
More on this topic
Project information
Pics
Plans
Products in use
Doka-automatic climbing formwork SKE
Doka large-area formwork Top 50
More on his topic
Rhine Bridge at Wesel
Webcam www. nrbw.de