| Using the self-climbing formwork at the tallest building in Wales. |
|
|
 |
|
Type of building:
|
High-rise building
|
|
Location:
|
Swansea / UK, Wales
|
|
start of construction:
|
February, 07
|
|
Total construction time:
|
~50 weeks
|
|
Construction time facade:
|
~12 months
|
|
 |
|
Height:
|
~90 m
|
|
Method:
|
Cores ahead
|
|
Step height:
|
regular section height 2,775m
|
|
Floors:
|
28
|
|
Steps:
|
28
|
|
 |
-
1-2 steps per week
-
SKE50 for core walls
-
GCS protection screen and GCS formwork is using in the facade
-
5cm wall thickness change
|
|
Organisation in Country: Doka UK
|
 |
|
Contact Engineering Amstetten
|
 |
|
 |
 |