This twin-tube motorway tunnel with 2 lanes in each tube has an overall length of 2,4 km.
100 pouring sections per tube, each 24 m long were necessarry to cast the twin-tubes. By using 2 Doka forming carriages 48 m per week were casted. |
|
|
 |
|
Type of building:
|
twin-tube motorway tunnel
|
|
Method:
|
cut and cover construction method
|
|
Production:
|
monolithic production
|
|
Location:
|
Wels, Austria
|
|
Formwork system:
|
Large-area formwork Top 50
|
|
Duration of insert:
|
1.5 years
|
|
 |
|
Purpose of the tunnel:
|
motorway tunnel
|
|
Section:
|
rectangular
|
|
inside width:
|
9.5 m
|
|
inside height:
|
5.5 m
|
|
Formed tunnel length:
|
2,400 m
|
|
Steps:
|
100
|
|
 |
The Tunnel Steinhaus was built in cut and cover construction method. Because of the ground water the whole section was casted in one pour (= "White tank" - i.e. as a water impermeable body of concrete with no additional impervious external skin).
All formwork movements were controlled by a central steering unit (- stripping of bottom panels, pulling back of wall panels and moving to the next pouring step).
|
 |
|
Strabag AG
|
 |
|
Organisation in Country:
|
Österreichische Doka
|
|
Department Amstetten:
|
Tunnel Expertise Centre
|
|
Project Manager:
|
Mr. Alois Schoißwohl
|
|
 |
|
 |
 |