| The Doka tunnel formwork carriage convinced by simple handling. |
|
|
 |
|
Type of building:
|
Tunnel
|
|
Method:
|
cut and cover construction method
|
|
Location:
|
Wörgl, Austria
|
|
Formwork system:
|
Doka large-area formwork Top 50
|
|
Duration of insert:
|
1 year
|
|
 |
|
Purpose of the tunnel:
|
Construction of the B178 - Loferer road
|
|
Section:
|
rectangular
|
|
inside width:
|
10,50 m
|
|
inside height:
|
5,25 m
|
|
Formed tunnel length:
|
1.185 m
|
|
Steps:
|
84
|
|
 |
|
The Tunnel´s length is 1,185 m and exept of one, short pouring step it is built in cut and cover construction method. For the length of 1,032m the ARGE bought the SL-1 formwork system that was used for the "Bypass Telfs" project.
|
 |
|
Arge Teerag-Asdag AG, Niederlassung Tirol - Held & Francke
|
 |
|
Organisation in Country:
|
Österreichische Doka
|
|
Department Amstetten:
|
DOKA Engineering Department
|
|
Project Manager:
|
Mr. Markus Stastny
|
|
 |
|
 |
 |