| This tunnel was built in cut and cover construction method. The tunnel´s shape is rectangular with chamfers between walls and slab. |
|
|
 |
|
Type of building:
|
Tunnel
|
|
Method:
|
cut and cover construction method
|
|
Location:
|
Telfs, Austria
|
|
Formwork system:
|
Doka large-area formwork Top 50
|
|
Duration of insert:
|
7 months
|
|
 |
|
Purpose of the tunnel:
|
By-pass
|
|
Section:
|
rectangular
|
|
inside width:
|
9.80 m / 8.06 m
|
|
inside height:
|
5.35 m
|
|
Formed tunnel length:
|
268 m
|
|
Steps:
|
25
|
|
 |
|
After the completion of the "By-pass Telfs" the formwork carriage was delivered to the Bruckhäusl job site. There it was modifiied and used for further 84 pouring steps.
|
 |
|
Arge Westumfahrung Telfs - Strabag/Teerag Asdag AG, Innsbruck
|
 |
|
Organisation in Country:
|
Österreichische Doka
|
|
Department Amstetten:
|
DOKA Engineering Department
|
|
Project Manager:
|
Mr. Markus Stastny
|
|
 |
|
 |
 |