Project information
Underground-extension Munich - Garching
The first 660 m of the new tube were built using the cut and cover construction method. A Doka forming carriage made of heavy-duty supporting system SL-1 and large-area formwork Top 50 was in use.
Project data
Type of building: Tunnel
Method: cut and cover construction method
Location: Garching, Germany
Formwork system: Doka large-area formwork Top 50
Duration of insert: 11 months
Building data
Purpose of the tunnel: Underground-extension
Section: rectangular
inside width: variable from 8.42 m - 9.26 m
inside height: 5,98 m
Formed tunnel length: 660 m
Additional info
The pouring sections were 15 m long, each week one was completed. The forming carriage adapted easily on the changing cross-section (between 8.42 m - 9.26 m).
Contractor
Alfred Kunz Ges.mbH, Amberg
Formwork design
Organisation in Country: Deutsche Doka
Niederlassung Nürnberg und Zentrale Maisach
Technical Manager: Mr. Johann Zillner
Project Manager: Mr. Peter Garatva
Department Amstetten: Tunnel Expertise Centre
Project Manager: Mr. Thomas Hochgatterer