| The lot 505 of the base tunnel Bodio started as a twin-tube section. At a length of 120 m it splits up into two separate tubes. The length of there tubes is 290 m each. |
|
|
 |
|
Type of building:
|
Tunnel
|
|
Method:
|
cut and cover construction method
|
|
Location:
|
Switzerland
|
|
Formwork system:
|
Doka large-area formwork Top 50, Doka heavy-duty supporting system SL-1
|
|
Duration of insert:
|
22 months
|
|
 |
|
Purpose of the tunnel:
|
railway
|
|
Section:
|
circular
|
|
inside width:
|
7,40 m
|
|
inside height:
|
7,40 m
|
|
Formed tunnel length:
|
twin-tube 120 m, two several tubes per 290 m
|
|
Steps:
|
64
|
|
 |
|
After 20 steps the twin-tube splits up. Only additional external formwork panels are placed.
|
 |
|
Mancini & Marti, Bellinzona
|
 |
|
Organisation in Country:
|
Holzco-Doka Schalungstechnik AG
|
|
Technical Manager:
|
Mr. August Morf
|
|
|
|
|
 |
|
 |
 |