Type of building:
|
Tunnel
|
|
Method:
|
Cut-and-cover construction method
|
|
Location:
|
Tyrol, Austria
|
|
Formwork system:
|
Doka large-area formwork Top 50, Doke heavy-duty supporting system SL-1
|
|
Duration of insert:
|
4 months
|
|
 |
|
Purpose of the tunnel:
|
Underpass
|
|
Section:
|
rectangular
|
|
inside width:
|
9.20 m
|
|
inside height:
|
5.28 m
|
|
Formed tunnel length:
|
185 m
|
|
Steps:
|
13
|
|
 |
Because of the short usage periode, board structure coated FF 20 formwork elements were used to decrease the assembly costs.
In the second step, the tunnel´s slab was formed by using a SL-1 table construction.
|
 |
|
Alpine Mayreder, Kematen
|
 |
|
Organisation in Country:
|
Österreichische Doka, Niederlassung West
|
|
Technical Manager:
|
Mr. Reinhard Luger
|
|
Project Manager:
|
Mr. Mario Scheiring
|
|
 |
|
 |
 |