| Doka delivered a slab formwork carriage for the dome-shaped slab. The tunnels length is 8,480 m. |
|
|
 |
|
Type of building:
|
Tunnel
|
|
Method:
|
Cut-and-cover construction method
|
|
Location:
|
Tyrol, Austria
|
|
Formwork system:
|
Doka large-area formwork Top 50, Doka heavy-duty supporting system SL-1
|
|
Duration of insert:
|
3 months
|
|
 |
|
Purpose of the tunnel:
|
Concentional rail tunnel
|
|
Section:
|
circular
|
|
inside width:
|
12.34 m
|
|
inside height:
|
3.82 m
|
|
Formed tunnel length:
|
410 m
|
|
Steps:
|
33
|
|
 |
To enable a fast moving, the Staxo scaffold was placed upon distribution girders consisting of rentable SL-1 beams.
The reduction of form ties and the small amount of lowering wedges enabled the site staff to move the carriage very fast to the next casting step.
|
 |
|
Strabag AG
|
 |
|
Organisation in Country:
|
Österreichische Doka, Niederlassung West
|
|
Technical Manager:
|
Mr. Reinhard Luger
|
|
Project Manager:
|
Mr. Mario Scheiring
|
|
 |
|
 |
 |