Type of building:
|
Tunnel
|
|
Method:
|
Cut-and-cover construction method
|
|
Location:
|
Brixen, Austria
|
|
Formwork system:
|
Doka large-area formwork Top 50, Doka heavy-duty supporting system SL-1
|
|
Duration of insert:
|
6 months
|
|
 |
|
Purpose of the tunnel:
|
By-pass
|
|
Section:
|
rectangular
|
|
inside width:
|
10.00 m
|
|
inside height:
|
5.02 m
|
|
Formed tunnel length:
|
410 m
|
|
Steps:
|
35
|
|
 |
Dokaplex coated Top 50 elements were used to cast the tunnel´s walls in the first construction step. The slab formwork, consisting of SL-1 components, followed some steps later.
The extension areas at the buildings end were supported by telescopable H16 beams, that were supported by floor props. The last blocks widened up that much, that additional Staxo loard-bearing towers had to be used.
|
 |
|
Ing. Hans Bodner Bauges.mbH & Co. KG
|
 |
|
Organisation in Country:
|
Österreichische Doka, Niederlassung West
|
|
Technical Manager:
|
Mr. Reinhard Luger
|
|
Project Manager:
|
Mr. Mario Scheiring
|
|
 |
|
 |
 |