| Hydraulic formwork operations for the Henndorf Tunnel |
| The result of building the new by-pass by the consortium of Arge Wayss & Freytag, Held & Francke and Habau should realize a 75 % reduction in traffic through Salzburg city Henndorf. |
|
|
 |
|
Type of building:
|
Tunnel
|
|
Method:
|
cut-and-cover construction method
|
|
Location:
|
Henndorf
|
|
Formwork system:
|
Doka heavy-duty supporting system SL-1, Large-area formwork Top 50
|
|
Duration of insert:
|
10 months
|
|
 |
|
Purpose of the tunnel:
|
By-pass to release traffic
|
|
Section:
|
circular
|
|
inside width:
|
10.44 m
|
|
inside height:
|
7.11 m
|
|
Formed tunnel length:
|
276 m + 456 m
|
|
Steps:
|
61
|
|
 |
Centre piece of the construction was a tunnel with a length of 1,418 m constructed by mining method. The North and South tunnels were constructed using a cut-and-cover construction method. Both 276 m and 456 m long sections utilized a full hydraulic tunnel formwork carriage from Doka.
Last year Held & Franche had already concreted the 1,100 m long avalanche protection construction “Erlachgalerie” in the Tyrolean Defreggental with a Doka tunnel formwork carriage. Held & Francke had purchased this formwork carriage earlier. The component parts were reused for the new formwork solution in the Henndorf tunnel.
|
 |
Consortium Tunnel Henndorf Wayss & Freytag, Habau, Held & Francke
|
 |
|
Organisation in Country:
|
Österreichische Doka
|
|
Technical Manager:
|
Mr. Markus Stastny
|
|
|
|
|
 |
|
 |
 |