By-pass Tunnel Henndorf
Hydraulic formwork operations for the Henndorf Tunnel
The result of building the new by-pass by the consortium of Arge Wayss & Freytag, Held & Francke and Habau should realize a 75 % reduction in traffic through Salzburg city Henndorf.
Project data
Type of building: Tunnel
Method: cut-and-cover construction method
Location: Henndorf
Formwork system: Doka heavy-duty supporting system SL-1, Large-area formwork Top 50
Duration of insert: 10 months
Building data
Purpose of the tunnel: By-pass to release traffic
Section: circular
inside width: 10.44 m
inside height: 7.11 m
Formed tunnel length: 276 m + 456 m
Steps: 61
Additional info
Centre piece of the construction was a tunnel with a length of 1,418 m constructed by mining method. The North and South tunnels were constructed using a cut-and-cover construction method. Both 276 m and 456 m long sections utilized a full hydraulic tunnel formwork carriage from Doka.

Last year Held & Franche had already concreted the 1,100 m long avalanche protection construction “Erlachgalerie” in the Tyrolean Defreggental with a Doka tunnel formwork carriage. Held & Francke had purchased this formwork carriage earlier. The component parts were reused for the new formwork solution in the Henndorf tunnel.
Contractor
Consortium Tunnel Henndorf
Wayss & Freytag, Habau, Held & Francke
Formwork design
Organisation in Country: Österreichische Doka
Technical Manager: Mr. Markus Stastny
  E-Mail: tunnel@doka.com