Project description
Metro in Athen, extension of line 2 (B) Station Slab
Metro in Athen, extension of line 2 (B)
"In 2 Metro Stations in Athen (Elliniko and Argiroupoli), a thick slab of 0.90 m had to be constructed. To enable an easy transportation of earth (out of the main tunnel) through the carriage a big passage had to be designed. Another critical factor was the fastest possible reuse of the formwork in the next concreting steps. Doka Hellas developed the idea of diagonal struts to lead the vertical forces to the existing platforms existing on both sides of the railway tracks."
Project data
Type of building: Tunnel
Method: Cut-and-cover construction method
Location: Greece
Formwork system: "Large-area formwork Top 50 Heavy-duty supporting system SL-1"
Duration of insert: 2.5 months in each station
Building data
Purpose of the tunnel: Railway
Section: rectangular
inside width (m): 14.50 m
inside height (m): 5.10 m
Formed tunnel length: 120 m in each station
Steps: 6 steps in each station
Contractor
Aktor Ate
Formwork design
Organisation in Country: Doka Hellas
Technical Manager: Mr. Vassilios Maniatakos
Project Manager: Mr. Dimitrios Liatsikas