Leipzig’s “City Tunnel” will pass beneath the centre of the city to link its two rail terminuses “Leipzig Hauptbahnhof” and “Bayrischer Bahnhof”. Three Doka SL-1 tunnel formwork travellers are in action on this project, fitted with 400 m² of Wall formwork FF20. Contract section C: Towards the north, the tunnel passes beneath Leipzig’s main railway station, leading to a section which is being constructed as a cut-and-cover tunnel complete with a flying junction. The 800 m long northern and western ramps, also built using the cut-and-cover method, will then link the tunnel to the existing overground network. |
|
|
 |
-
Type of building: Tunnel in cut & cover construction method
-
Usage: Railroad tunnel - Typical cross section
-
Location: Leipzig
-
Start of construction - Doka systems: 05/2008
-
Period of use - Doka systems: 12 months
|
-
Method: monolithic construction method
-
Cross section: rectangular
-
Inside width: approx. 6,00 m
-
Inside height: approx. 6,80 m
-
Formed tunnel length: 320 m
-
Step length: 10,0 m
-
Steps: 32
|
-
The wall and slab formwork FF20 was delivered to the site ready to use.
-
The formwork traveller consisted almost entirely of rentable standard parts.
|
|
ARGE City Tunnel Leipzig Los C
|
 |
|
 |
 |