| The approx. 3.9 km long by-pass around the town of Bad St. Leonhard is currently the second-largest construction project in Austria’s southern province of Carinthia. The contract section is divided into four subsections. Contractors Massivbau and Doka worked together very closely to design a highly cost-effective tunnel formwork traveller that incorporated as much of the client’s existing stocks of equipment as possible. This traveller is enabling the construction firm to cast in a weekly cycle. |
|
|
 |
-
Type of building: Tunnel in cut & cover construction method
-
Usage: Road tunnel – Typical cross section
-
Location: Bad St. Leonhard
-
Start of construction – Doka systems: 09/2009
-
Period of use – Doka systems: 7 months
|
-
Method: Semi-monolithic construction method
-
Cross section: rectangular
-
Inside width: 10,54 m
-
Inside height: 5,77 m
-
Formed tunnel length: 500 m
-
Step length: 20,00 m
-
Steps: 25
|
|
Massivbau
|
 |
|
 |
 |