Adaptable travelling tunnel-formwork unit for funnel-shaped cavern
|
|
|
 |
|
Type of building:
|
tunnel
|
|
Method:
|
mining method
|
|
Location:
|
Frutigen, Switzerland
|
|
Formwork system:
|
Large-area formwork Top 50
|
|
Duration of insert:
|
4 months
|
|
 |
|
Purpose of the tunnel:
|
railway
|
|
Section:
|
circular
|
|
inside width (m):
|
13,1 m - 7,6 m / 18,1 m - 13,1 m
|
|
inside height (m):
|
9,95 m - 7,95 m / 9,95 m - 9,65 m
|
|
Formed tunnel length:
|
275 m
|
|
Steps:
|
16 / 12
|
|
 |
The formwork was folded down hydraulically and abridged after each pouring step.
|
 |
Arge SATCO - Schweizer Alp Transit Consortium Contact: Mr. Häfliger
|
 |
|
Organisation in Country:
|
Holzco-Doka
|
|
Technical Manager:
|
Mr. August Morf
|
|
Department Amstetten:
|
Tunnel Expertise Centre
|
|
Project Manager:
|
Mr. Martin Wenger
|
|
 |
|
 |
 |