| For the production of the emergency pull-over tunnel a formwork carriage with a length of 10.25 m was used. |
|
|
 |
|
Type of building:
|
Tunnel
|
|
Method:
|
mining method
|
|
Location:
|
Hornberg, Germany
|
|
Formwork system:
|
Doka large-area formwork Top 50
|
|
Duration of insert:
|
4 months
|
|
 |
|
Purpose of the tunnel:
|
By-pass Hornberg
|
|
Section:
|
circular
|
|
inside width:
|
15.72 m
|
|
inside height:
|
9.13 m
|
|
Formed tunnel length:
|
80 m
|
|
Steps:
|
8
|
|
 |
|
The building with a two lane standard cross section includes portals, built in cut and cover construction method, two emergency pull-over tunnels and an emergency gallery with five air locks.
|
 |
|
Arge Tunnel Hornberg (Strabag AG, Hermann Kichner GmbH & Co. KG)
|
 |
|
Organisation in Country:
|
Österreichische Doka
|
|
Department Amstetten:
|
Tunnel Expertise Centre
|
|
Project Manager:
|
Mr. Martin Wenger
|
|
 |
|
 |
 |