Service cavern UXC55 and USC55 at the Cern Point 5
|
|
|
 |
|
Type of building:
|
Service cavern
|
|
Method:
|
Mining method
|
|
Location:
|
Meyrin, Switzerland
|
|
Formwork system:
|
Doka large-area formwork Top 50
|
|
|
|
|
Duration of insert:
|
Cavern UXC55: 3 months
Cavern USC55: 5 months
|
|
 |
|
Purpose of the tunnel:
|
Service cavern for particle accelerator
|
|
Section:
|
circular
|
|
inside width (m):
|
Cavern UXC55: 25,0 m
Cavern USC55: 18,0 m
|
|
inside height (m):
|
Cavern UXC55: 27,0 m
Cavern USC55: 15,0 m
|
|
Formed tunnel length:
|
137 m
|
|
Steps:
|
14
|
|
 |
The front sided walls were formed by supporting construction frames and dam formwork D15K.
|
 |
Dragados, Spain Seli, Italy
|
 |
|
Organisation in Country:
|
Österreichische Doka
|
|
Department Amstetten:
|
DOKA Engineering Department
|
|
Technical Manager:
|
Mr. Markus Stastny
|
|
 |
|
 |
 |