| This project involves the refurbishment of an existing circular-section tunnel originally excavated by mining. The project entailed casting 12 concreting sections with a maximum section length of 12.0 metres. The extent of preassembly was high, so once on site the tunnelling carriage was very quickly readied for use. |
|
|
 |
|
Type of structure:
|
Tunnel
|
|
Mode of construction:
|
Mining method
|
|
Location:
|
Predlitz-Turrach, Austria
|
|
Formwork system:
|
Doka beam formwork Top 50, Doka heavy-duty supporting system SL-1
|
Formwork system in use for:
|
1,5 months
|
|
 |
|
Purpose of the tunnel:
|
Refurbishment
|
|
Section:
|
Circular
|
|
inside width:
|
10,10 m
|
|
inside height:
|
6,70 m
|
|
Formed tunnel length:
|
120 m
|
|
Steps:
|
10
|
|
 |
G. Hinteregger & Söhne Baugesellschaft mbH
|
 |
|
Organisation in Country:
|
Österreichische Doka
|
|
Project Manager:
|
Mr. Markus Stastny
|
|
 |
|
 |
 |