Automotive formwork carriage for the tunnel Kirchham
|
|
|
 |
|
Type of building:
|
tunnel
|
|
Method:
|
top cover construction method
|
|
Location:
|
Kirchham/Maishofen
|
|
Formwork system:
|
Large-area formwork Top 50
|
|
Duration of insert:
|
2 months
|
|
 |
|
Purpose of the tunnel:
|
removal of the main road
|
|
Section:
|
rectangular
|
|
inside width (m):
|
10,00 m
|
|
inside height (m):
|
5,43 m
|
|
Formed tunnel length:
|
380 m
|
|
Steps:
|
31
|
|
 |
The supporting scaffold SL-1 as formwork carriage for vertical facing of the sheet pilings. The concrete for both walls is poured simultaneously.
|
 |
ARGE Umfahrung Kirchham (Porr AG, G. Hinteregger & Söhne Bauges.mbH, Swietelsky Bauges.mbH, Strabag AG)
|
 |
|
Organisation in Country:
|
Österreichische Doka - Niederlassung Salzburg
|
|
Technical Manager:
|
Mr. Josef Palme
|
|
Department Amstetten:
|
Engineering Department
|
|
Project Manager:
|
Mrs. Dagmar Ziegler
|
|
 |
|
 |
 |