Slab formwork with integrated pile cap formwork Substructure: Doka heavy-duty supporting system SL-1 Top structure: WU220-profiles + Timber beam formwork FF20 (by site) |
|
|
 |
|
Type of building:
|
Tunnel
|
|
Method:
|
Top cover construction method
|
|
Location:
|
Linz, Austria
|
|
Formwork system:
|
Doka large-area formwork Top 50
|
|
Duration of insert:
|
3,5 months
|
|
 |
|
Purpose of the tunnel:
|
Noise protection project
|
|
Section:
|
rectangular
|
|
inside width (m):
|
15,00 m
|
|
inside height (m):
|
3,00 m
|
|
Formed tunnel length:
|
200 m
|
|
Steps:
|
6
|
|
 |
-
500 m² slab per pouring step were formed. Because of the small tunnel radii the formwork was divided lengthwise into two smaller formwork sets.
-
The carriage is 2 x 16.5 m long and consits of four length beams and 14 cross-framework beams. The construction weighs 165 tons.
|
ARGE A7 Betonbau (Strabag, Alpine Mayreder, Porr, Held & Franke) Contact: Mr. Ecker, Mr. Knollmüller
|
 |
Organisation in Country: Österreichische Doka - Niederlassung Oberösterreich Mr. Martin Zabern (Project Manager)
Department Amstetten: Tunnel Expertise Centre Mr. Christian Heuböck (Head of Tunnel Expertise Centre)
|
 |
|
 |
 |