| Mobile formwork carriage for the facing of the sheet pilings. One pouring step was poured every day. |
|
|
 |
|
Type of building:
|
Tunnel
|
|
Method:
|
Top cover construction method
|
|
Location:
|
Linz, Austria
|
|
Formwork system:
|
Doka large-area formwork Top 50
|
|
Duration of insert:
|
2,5 months
|
|
 |
|
Purpose of the tunnel:
|
Noise protection project
|
|
Section:
|
rectangular
|
|
inside width (m):
|
7,25 m - 8,75 m
|
|
inside height (m):
|
4,30 m
|
|
Formed tunnel length:
|
212 m
|
|
Steps:
|
20
|
|
 |
-
The formwork carriage with a total weight of 67 t is 14 m long and changes from a width of 7.25 m to a width of 8.75 m.
|
ARGE A7 Betonbau (Strabag, Alpine Mayreder, Porr, Held & Franke) Contact: Mr. Lerchbaumer, Mr. Knollmüller
|
 |
Organisation in Country: Österreichische Doka - Niederlassung Oberösterreich Mr. Martin Zabern (Project Manager)
Department Amstetten: Tunnel Expertise Centre Mr. Christian Heuböck (Head of Tunnel Expertise Centre)
|
 |
|
 |
 |