In the course of the Vienna International Airport expansion an already existing railway tunnel which undercrosses the airport runways had to be strengthened.
|
|
|
 |
|
Type of building:
|
Tunnel
|
|
Method:
|
Top cover construction method
|
|
Location:
|
Vienna, Austria
|
|
Formwork system:
|
Doka heavy-duty supporting system SL-1
|
|
|
Doka framed formwork Framax Xlife
|
|
|
Doka large-area formwork Top 50
|
|
Duration of insert:
|
9 months
|
|
 |
|
Purpose of the tunnel:
|
Railway tunnel
|
|
Section:
|
rectangular
|
|
inside width:
|
5.50 m
|
|
inside height:
|
6.90 m
|
|
Formed tunnel length:
|
730 m
|
|
Steps:
|
87
|
|
 |
For reasons of fire protection the railway tunnel had to be strengthened between the existing sheet pilings. Therefore a 45 cm thick fibre reinforced wall facing with integreated slab brackets were casted. This measure ensures the construction´s static resistance in case of fire.
|
 |
Porr Technobau und Umwelt AG Kontakt: Mr. Dipl.-Ing. Harald Metzinger, Mr. Ing. Georg Pleva
|
 |
|
Organisation in Country:
|
Ă–sterreichische Doka, Niederlassung Wien
|
|
Project Manager:
|
Mr. Thorsten Kirchweger
|
|
 |
|
 |
 |