Type of building:
|
Office building
|
|
Location:
|
Zurich, Switzerland
|
|
Start of construction:
|
May,2001
|
|
Total construction time:
|
~ 18 month
|
|
Construction time cores:
|
~ 15 month
|
|
 |
|
Height:
|
72 m + 88 m
|
|
Method:
|
core ahead
|
|
Step height:
|
Regular step height 3,30 m
|
|
Floors:
|
28
|
|
Steps:
|
28
|
|
 |
-
5 days cycle
-
Concrete placing boom raised with platform SCP
-
Suspended stair tower to get up to the platform SCP
-
One platform SCP used on both towers
|
ARGE: Fa. Züblin Schlittler Bau AG, Fa. Brunner Erben AG Zürich, Fa. Batigroup AG
Contact: Mr. Waldschmidt
|
 |
|
Organisation in country: Holzco Doka
|
 |
|
Contact Self-climbing Systems Expertise Centre
|
 |
|
 |
 |