Doka - The Formwork Experts
Conesco
News
Fairs & Events
Formwork News
01
 
Automated tunnel-formwork unit for Stans Tunnel
Forming operations at the push of a button
As part of the upgrading of the Munich-Verona railway corridor through Tyrol, a new, 40 km stretch of two-track railway is under construction in the Lower Inn Valley. Contract section H4-3, “Stans”, requires the building of a basement waterproofing construction and of a 2615 m long tunnel, partly using cut-and-cover methods, partly driven by underground means. To cast a 55 m long section of the cut-and-cover tunnel, contractors Alpine Mayreder opted for a hydraulically travelled tunnel-formwork unit from Doka.
The extremely cramped site conditions rule out crane-lifting of the outside formwork. For this reason, it is designed as a telescopic three-hinged arch.
The difficult boundary conditions presented the site crew and formwork technicians with some tough challenges: The water table is only a very few metres beneath ground level, meaning that the building pits have to be waterproofed with sheet-pile walls and an underwater-concrete invert. As the tunnel structure will be entirely in groundwater after completion, the 67 concreting sections all have to be constructed in “waterproof tank” quality, with double joint-sealing tapes. The cramped site conditions make matters even more difficult: There is only 1.20 m of space left for the formwork – and for operating the formwork – between the outside wall of the tunnel and the sheet-pile wall. Because the back-stay anchoring of the sheet-pile walls protrudes into this clearance zone, lifting the outside formwork of the tunnel by crane was practically out of the question.

Instead, Doka Engineering planned and supplied a self-travelling “tunnel formwork machine” assembled from rentable system components. It consists of an all-hydraulic inside tunnel-formwork unit and an outside tunnel-formwork unit that can be repositioned with no need for a crane. The inside travelling tunnel-formwork unit is based on a framework made of SL-1 components, onto which fold-away elements of Top 50 large-area formwork have been fitted. Its 8 hydraulic cylinders and 2 hydraulic motors enable the forming operations to go ahead at the push of a button. Setting up and striking the two formwork-halves; lifting and lowering the tunnel-formwork unit and then travelling it on rails using flanged wheels – all this is done 100% hydraulically. The outside formwork can also be repositioned by the site crew in one piece, on roller blocks – again, with no need for a crane. For this, Doka designed the two formwork-halves as a telescopic three-hinged arch.

To save even more time, the Formwork Experts reinforced all the timber-beam formwork elements with Steel walings WU 16 and used 20 mm diameter form-ties. This has saved the crew 40 % of the wall-ties in each casting section. For 67 weekly cycles in all, that means at least 2500 fewer wall-ties! The manhours that would otherwise have gone into these wall-ties can now be used elsewhere. There is also less risk of water-permeable points on the structure.

Alpine Mayreder’s supervisor Kurt Knollmüller is very satisfied with how the forming operations have been proceeding. “An ingenious formwork system like this saves a lot of time on the site. And time, as we all know, is money!”

Bauausführung: Alpine Mayreder
Schalungsberatung: Kompetenzcenter Tunnel und Doka-NL Inzing
Articles
Editorial
Doka showcasing innovations at bauma 2007
A warm welcome to bauma 2007
Safety speeds up the forming operations
Success from innovational strength and closeness to clients
Table Lifting System revolutionises construction workflows
Doka practical tip
Dokaset = super-fast formingtimes + superlative safety
Automated tunnel-formwork unit for Stans Tunnel
Doka in brief
Complex pylons formed with Climbing formwork SKE 50
More on this topic
Project information