calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb

Tishreen Cooling Tower

Syrian Arab Republic

A new gas and steam power station block is built at the Tishreen Power Station. The process includes construction of a cooling tower that is 111.00m high. For this project, a total of 76 cooling tower formwork units SK175 were used. The cooling tower was constructed within record time of 4 - 5 months.

Back

Project data

Year of completion
2009
Project duration
5 Months
Country
Syrian Arab Republic
Realization
Tosee Sioha Co.
Structure
Thermal power station
Type of structure
Industrial structures

Cooling tower

Construction method
Curved/round
Structure height
111 m
Height of casting sections
1.5 m
Number of casting sections
58
Cycle time
1 -day cycle
Form-tie pattern
Stipulated by architect