|
The supervisor must perform a complete sight-check of the following elements to ensure that they are correctly installed and that no damage or defects have occurred. |
|
CONTRACTOR: |
SUPERVISOR: |
|||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
CONSTRUCTION PROJECT: |
INSTALLATION PERIOD: |
|||||||||||||
SERIAL NUMBER OF THE LOADING PLATFORM: |
USAGE LOCATION: |
|||||||||||||
POS |
ELEMENT TO BE CHECKED |
CHECKED |
||||||||||||
1 |
Main beam |
No visible damage |
|
|||||||||||
2 |
Platform decking |
No visible damage + bolted to main beams |
|
|||||||||||
3 |
Crane lifting points |
No visible damage to steel lifting eyes and weld seams |
|
|||||||||||
4 |
Railings |
No visible damage + all threaded fasteners/pins installed |
|
|||||||||||
5 |
Floor props |
Screw-jack function |
|
|||||||||||
6 |
Floor props |
Security of hinge plate to prop foot and to main beam |
|
|||||||||||
7 |
Floor props |
Security of diagonal brace connector |
|
|||||||||||
8 |
Diagonal brace |
Installed |
|
|||||||||||
9 |
Floor props |
Floor props vertically upright on the main beams |
|
|||||||||||
Before disconnecting from the crane: |
||||||||||||||
10 |
The loading platform is correctly positioned (end cross-beam of the decking must be tight against the slab edge). |
|
||||||||||||
11 |
The floor props are screwed tight and force-locked against the slab or the anchorages through the slab are installed. |
|
||||||||||||
12 |
Anchorages for the horizontal loads are installed on both main beams. |
|
||||||||||||
13 |
Edge protection system is in place up to the loading platform on both sides. |
|
||||||||||||
Notes (record of deformations / damage / incorrect installation, etc.) |
||||||||||||||
DATE: |
SIGNATURE: |
|||||||||||||
.