calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb

​First Doka OneGo project successfully ongoing in Brazil

10.09.2014 | News
500 m² of the new monolithic formwork Doka OneGo are in use for the construction of 264 twin-houses in Jaboticabal (Brazil).

Press Contact

Impressions

Every day a new twin-house is built. The one day-cycle comprises the stripping of the previous casting step, the set up of the formwork and the pouring. The construction company uses self-compacting concrete (SCC) to further speed up the construction progress. The easy and smooth forming and stripping processes as well as the light weight of the elements compared to competitors have been highly commended by the construction team. That’s a proof that Doka OneGo lives up its slogan “Go fast, build smart!”.

Residencial Vida Nova
Jaboticabal, Brazil
Contractor: Magma
Subcontractor: i9 tec

This could also be of interest for you:

Doka renews partnership with Habitat for Humanity

07.05.2025 | News

Shaping Toronto’s skyline and reaching new heights at One Bloor West

14.05.2025 | Press

Do you have any questions on the article? Get in touch with us!

Fields marked with * are required.
* Please fill out all required fields!
    Message could not be sent – please try again a little later!