calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb
I consent to the use of cookies by this website for analyses and personalised content. Find out more OK
I consent to the use of cookies by this website for analyses and personalised content. Find out more OK

Millennium Pylon bridge

Montenegro

Even very complex projects can be built easily, safely and quickly using Climbing formwork MF.

Back

Project data

Year of completion
2005
Project duration
7 Months
Country
Montenegro
Address
Podgorica
Realization
Primorje, Alpine-Mayreder & Freyssinet
Structure
Bridge
Type of structure
Piers and pylons

Pylon

Construction method
Inclined
Structure height
57 m
Height of casting sections
3.30 m
Number of casting sections
18
Cycle time
14 -day cycle