calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkclose
Contact

A11 Belgium

Belgium

A variety of widely differing techniques were used to construct the 12-km A11 motorway link between Bruges and Westkapelle. Construction of the 1.5-km long viaduct involves movable scaffolding, and the railway tunnela are cut-and-cover. A logistical project in a class of its own.

Challenges:

• flexible formwork solution for the movable scaffold for building the viaduct
• detailed logistics planning for dealing with several construction sections involving different methods of construction (bridge, tunnel)

Solution:

Construction of the one-and-a-half kilometre viaduct on the far side of the first motorway intersection in Bruges by the movable scaffolding technique.

Zurück zur Übersicht
Reference Title
Reference Title
Reference Title

Project data

Year of Completition
2017
Projektdauer
3 Years
Country
Belgium

Building Data

Viadukt
1.5 km