calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlink
I consent to the use of cookies by this website for analyses and personalised content. Find out more OK
I consent to the use of cookies by this website for analyses and personalised content. Find out more OK
United Kingdom

A228 Stoke Bridge

United Kingdom

In view of the use of pre-cast concrete members between the main beams, the contractors AINSWORTH CIVILS & ENG.LTD once again opted for Bridge formwork ParaTop from Doka. At the time, this project was the biggest deployment of this new formwork system, which adapted perfectly to the pre-determined head-bolt positions.

Back to overview
Perfect adaptability to the radius
Operability from above, for safe working

Project data

Year of completion
2011
Project duration
5 Months
Country
United Kingdom
Address
A228 Stoke Bridge, Stoke, Isle of Grain
Postcode
ME3
Town or city
Isle of Grain, Kent
Realization
AINSWORTH CIVILS & ENG.LTD
Structure
Bridge
Type of structure
Composite construction

Bridge deck/superstructure

Construction method
Straight
Length of bridge (superstructure)
250 m
Width of bridge (superstructure)
13 m
Height of bridge (up to top edge of superstructure)
10 m
Cross-sectional shape of structural steelwork
I-section girder
Clear width of structural steelwork
8
Clear height of structural steelwork
2
Length of concreting section
82 m
Number of casting sections
3