calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapcontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuser
I consent to the use of cookies by this website for analyses and personalised content. Find out more OK

Westbahn Tunnel at Stans

Austria

This 634 m long railway tunnel was built by Alpine Bau GmbH using the cut-and-cover method. A high-performing Doka tunnel slab traveller was in service here for the cover slab, which has a haunched cross-section. Owing to the varying cross-sectional shape, Doka planned an easily adaptable tunnel formwork
traveller that was designed to separate in the middle.

Back to overview
Westbahn Tunnel, main contract section H4-3 Stans
Westbahn Tunnel, main contract section H4-3 Stans

Project data

Year of completion
2009
Project duration
18 Months
Country
Austria
Address
Stans, Tyrol, Austria
Contractors
Alpine Bau GmbH
Structure
Tunnel
Type of structure
Cut-and-cover tunnel

Wall

Construction method
Segmented (non-monolithic)
Cross-sectional shape
Rectangular
Clear width
17.08 m
Clear height
8.50 m
Formed length of tunnel
634 m
Length of concreting section
12 m
Number of casting sections
55
Cycle time
7 -day cycle