calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb

Resource and Energy Center

Hamburg, Germany

Doka UniKit: Reliable beyond calculation

During the expansion and redevelopment of a power plant, Doka UniKit brings its own power to the job – easily mastering even the most unpredictable loads.

On behalf of Stadtreinigung Hamburg, a waste incineration plant is being transformed into a state-of-the-art Resource and Energy Center (ZRE) – an important building block for the city’s sustainable energy supply. The executing joint venture ARGE ZRE Stellingen (Wayss & Freytag/Matthäi/Heitkamp) teamed up with Doka to deliver formwork and shoring solutions. One of the most complex tasks: safely transferring enormous, hard-to-calculate loads during the construction of a wall of over 18 m above an open area. A customized solution with Doka UniKit towers 480 ensures both load-bearing capacity and cost efficiency. And thanks to the involvement of Doka’s pre-assembly experts, the time-critical conditions can also be reliably met.

Back to overview

Building type
Power plant

Challenge
Supporting an over 18 m high wall built using slipform construction, without a base, subject to enormous and constantly increasing loads, with a tight schedule for erection and dismantling

Solution
UniKit 480 towers as a strong and flexible shoring solution on a substructure of UniKit primary beams for safe, precise load transfer at the structure’s perimeter; a detailed assembly and dismantling concept, developed and implemented in cooperation with Doka’s pre-assembly team, ensured meeting the tight schedule

further project data

Milestone in the Energy Transition

With the Resource and Energy Center (ZRE), one of Europe’s most modern waste utilization facilities is being built on the site of the former waste incineration plant Stellinger Moor in Hamburg’s Bahrenfeld district. The new center integrates mechanical sorting, material recovery, and thermal treatment. To achieve this, the existing plant is being extensively modernized and significantly expanded in order to recover valuable resources such as glass, plastics, metals, and paper, while at the same time ensuring an efficient supply of electricity and heat. This unique combination of waste management and energy generation marks a key milestone in Hamburg’s energy transition.

Partner for Complex Concrete Challenges

The joint venture ARGE ZRE Stellingen – consisting of Wayss & Freytag Ingenieurbau AG, Matthäi Bauunternehmen GmbH & Co. KG and Heitkamp Industrial Solutions GmbH – is responsible for delivering this large-scale project. To manage the demanding concrete works safely and efficiently, they rely on strong partners. Since autumn 2023, Doka has been supplying a wide range of formwork systems for walls, slabs, and shoring (including framed formwork Framax Xlife plus, timber-beam floor formwork Dokaflex, load-bearing towers Staxo 40, Staxo 100 and heavy-duty supporting system SL-1). These high-performance systems are in use throughout all project phases – from dismantling and refurbishing existing concrete structures to constructing new sections of the bunker.



18 Meters of Concrete – with Nothing Below

One of the many engineering challenges on this major construction site: erecting an 18 m high “bottomless” wall above an open space – meaning there is nothing underneath to carry the load. That alone makes the transfer of forces highly complex. Added to this, the ambitious schedule requires the wall to be constructed using slipform technology, which increases the demands on the shoring structure. With every meter poured, the loads increase and shift continuously. Against this backdrop of “unpredictability,” a particularly reliable, flexible, and safe load-bearing solution is required – a task that Doka’s heavy-load experts handle with engineering precision and a keen eye on cost efficiency.

Stable Beyond the Perimeter

To develop a statically optimized shoring solution, the team turned to Doka’s universal engineering kit, Doka UniKit. The chosen solution: UniKit towers 480 – economical, adaptable to the site conditions, and, above all, easy to handle. Special features such as a substructure of cantilevered HEB 400 primary beams ensure the towers can be stably positioned beyond the structure’s perimeter, transferring vertical loads safely back into the building. Distribution beams direct the enormous forces precisely and evenly into load-bearing sections of the existing slab. Where the existing structure is insufficient, additional supporting measures are implemented.

Equally important to safe load transfer is ensuring the safety of the site crew throughout construction. For this reason, the areas below the new wall are extensively shored and temporary protection decks are installed at tower height. This measure serves purely as occupational safety, reliably preventing falling hazards and ensuring secure working conditions.

Load-Bearing Capacity on a Countdown

True to the principle “Think about dismantling while still assembling!”, the entire shoring phase was meticulously planned in advance. To guarantee the timely release of the next construction stage, the assembly of the towers, concreting of the wall, and subsequent dismantling all had to be completed within a clearly defined time frame. For dismantling, just one month was available – a very tight window. The UniKit solution was therefore designed not only to deliver maximum load-bearing capacity, but also to allow for rapid, safe assembly and disassembly. In this regard too, the UniKit towers 480 proved ideal: lighter and more flexible to handle than other systems, they can be erected and dismantled significantly faster. Together with Doka’s pre-assembly specialists (SVM), the shoring experts also developed a detailed installation and dismantling concept that streamlined processes and optimized material logistics. Doka supervisors were on site to oversee every step – ensuring that every crane lift was executed flawlessly. This made it possible to complete the towers on schedule and free up the site in time for subsequent trades.

Edgar Feist, Project Engineer in charge for the project at Doka, sums it up: “On large-scale projects, it’s crucial that all building blocks interlock perfectly. With Doka UniKit, we had exactly such a building block – one that made even the unpredictable calculable and kept the tight schedule achievable.”


Project data

Construction start
2022
Period of use of Doka UniKit
April to August 2025

Country
Germany
ZIP Code
22113

Contractor
Stadtreinigung Hamburg
Construction company
ARGE ZRE Stellingen (Wayss & Freytag/Matthäi/Heitkamp)