calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb

Runway tunnel, Vienna Airport

Austria

Implementation of a new tunnel safety concept made it necessary for a tunnel to be structurally reinforced. This was done by adding a 45cm thick fibre-concrete inliner, with integrated corbels, between the existing bored piles of the tunnel,
for fire-safety reasons.

Back

Project data

Year of completion
2007
Project duration
9 Months
Country
Austria
Town or city
Vienna
Realization
Porr Technobau und Umwelt AG
Structure
Tunnel
Type of structure
Top-cover method

Wall

Construction method
Inliner
Cross-sectional shape
Rectangular
Clear width
5.50 m
Clear height
6.90 m
Formed length of tunnel
730 m
Length of concreting section
8.40 m
Number of casting sections
87
Cycle time
1 -day cycle