In Corpus Christi, a new US 181 Harbor Bridge is being constructed to replace the existing bridge that crosses the Corpus Christi Ship Channel. A new bridge is necessary to replace the current aging bridge and to permit larger ships to pass beneath, with a 205-foot clearance. When complete, the US 181 Harbor Bridge will be the tallest point in South Texas and the longest cable-stay concrete segmental bridge in the United States.
Press Contact
Impressions
Doka was brought on the job because of our experience and unique solutions. The challenge was to come up with a way to reuse the same formwork from pour to pour with continually changing geometry. The upper and lower pylons were very different shapes requiring two unique designs. The primary pylon structures have a unique geometry that narrows and angles at the same time. A reusable system was needed that would have minimal changes between pours. Doka worked with the customer to collaborate on the formwork designs, and ensuring that the final solution was exactly what was required.
To do this, Doka used large-area formwork Top 50 as well as hydraulic climbing formwork SKE50 and SKE100 platforms. The platform system was designed with telescopic platforms that adjust to the changing pylon shape.
Doka helped the contractor with the schedule because there was minimal rebuild between pours. Doka also saved crane time due to the hydraulic lifting systems employed. The contractor is happy with the overall operation of the formwork system as well is the engineering backup received.
When completed, this new bridge will open up the port of Corpus Christi to larger ships and possibly even a Cruise ship terminal.
Project Facts:
Location: Corpus Christi, TX
Type of project: Cable Stay Bridge Square footage: 5,580 sq. ft. of formwork for one pylon
General contractor: Flatiron Dragados JV Concrete contractor: Flatiron Dragados Overall project cost: $900 million
Construction time: Began in early 2018 and projected completion is late spring 2020.
Joining forces: Malaysian-based MFE Formwork Technology is now part of Doka
02/20/2024
|
Press
Austria/Malaysia, Feb. 16, 2024 – Doka, a global leader in formwork and scaffolding, now combines its strengths with Malaysian-based MFE Formwork Technology, a market leader in monolithic aluminum formwork.
Hyundai Electric Vehicle Plant Fast-Tracks Multiple Projects
10/19/2023
|
Press
OCTOBER 19, 2023 – KENILWORTH, NJ – Doka USA – the leader in providing innovative formwork and safety solutions announces Doka’s involvement in a massive three building Hyundai Motors project that is relying on a fast timeline.
Do you have any questions on the article? Get in touch with us!
Thank you for your interest - The Longest Cable-Stay Bridge in the US Rises with Doka.
Please, fill in the form below to receive more information on this topic and access it conveniently from your email later.
All listed fields are required.
By using our site, necessary cookies are set on your device for the execution of the service. Find out more in our data privacy policy
https://www.doka.com/data-privacy.
Thank you very much for your interest - The Longest Cable-Stay Bridge in the US Rises with Doka.
A link with further information has been sent to the provided e-mail address.
You can now switch back to the QR code reader to request information on other topics. You have the option to save your contact details to be automatically used for your next request.
Settings for cookies and third-party applications
Cookies and third-party applications are used on our website. This helps us to guarantee the best possible performance of our website, especially
the constant improvement of the functionality of our website (analysis of the user visit),
a smooth shopping experience when using the Doka online shop or
the placement of suitable advertising for users on certain platforms.
Do you consent to the use of cookies and the processing of personal data associated therewith?