I consent to the use of cookies by this website for analyses and personalized content.
Find out more OK
Building Bigger Sewers to Accommodate Growth
04.10.2017 |
US
In Southern Ontario, Canada, immediately east of Toronto in Durham Region, is the growing area of Markham/Pickering. This area is designated to receive more development and population in the coming years, straining the current sanitary sewer resources. To handle the upcoming growth, a trunk sewer was contracted to accommodate the additional sanitary sewer flows projected from the future growth.
Press Contact
The goal of this sewer project is to carry 100 percent of the 2036 design sanitary sewer flows projected from future growth. The new Southeast Collector (SEC) Trunk Sewer is approximately 14 kilometers in length. The sewer is to be constructed at depths of 5 meters to more than 40 meters below the ground surface.
A major challenge of this project was to ensure that the pipeline stayed within the Newmarket Till soil stratum, which is more conducive material for tunnel construction. To do so, a substantial drop in elevation of the pipeline over its length was needed. The use of an Earth Pressure Balance Machine as a tunnel boring machine allowed for different modes of operation to accommodate the changing soil conditions.
Custom Formwork Solution
Doka was able to secure this project due to their expertise in 3D engineering design and custom-built formwork solutions. Strabag, the contractor, relied on Doka to meet extremely tight project deadlines and to deliver high-quality custom-built formwork panels ready to use on site.
Doka supplied the custom benching formwork for 13 ventilation shafts in total, ranging between 10- to 60-meter depths. The custom formwork panels allowed Strabag to pour the U-shaped benching at the bottom of each ventilation shaft connecting the newly drilled tunnel openings with each other.
These custom formwork panels were based on Doka’s large-area formwork Top 50, including wooden gussets and custom splices. Each custom formwork element was highly complex and different in shape and size, but the Doka pre-assembly team of Toronto rose to the challenge and met all customer needs. Every single formwork element was hand-built and assembled to the highest possible standards in the formwork industry. Doka’s local engineering department, together with the Competence Centre in Austria, played a key role in successfully designing this challenging custom formwork solution for Strabag.
Meeting Town Requirements
The final concrete finish was also extremely important to the client. The town of Markham required the use of Zemdrain, a form liner to be installed on every formwork element prior to a concrete pour. Doka’s custom formwork panels were epoxy-coated during the assembly process and shipped to the site ready to use. The achieved concrete finish was of high standard, comparable to Zemdrain, and was therefore accepted by the client. Doka’s custom formwork solutions and the good teamwork between Doka and Strabag made this project an overall success.
The Facts Project name: SEC Trunk Sewer Location: Markham/Pickering, Ontario, Canada. Type of project: Trunk sewer General contractor and/or architect: Strabag Concrete contractor: Strabag
Product used
Custom-designed large area formwork Top 50
Joining forces: Malaysian-based MFE Formwork Technology is now part of Doka
02/20/2024
|
Press
Austria/Malaysia, Feb. 16, 2024 – Doka, a global leader in formwork and scaffolding, now combines its strengths with Malaysian-based MFE Formwork Technology, a market leader in monolithic aluminum formwork.
Hyundai Electric Vehicle Plant Fast-Tracks Multiple Projects
10/19/2023
|
Press
OCTOBER 19, 2023 – KENILWORTH, NJ – Doka USA – the leader in providing innovative formwork and safety solutions announces Doka’s involvement in a massive three building Hyundai Motors project that is relying on a fast timeline.
Do you have any questions on the article? Get in touch with us!
Thank you for your interest - Building Bigger Sewers to Accommodate Growth.
Please, fill in the form below to receive more information on this topic and access it conveniently from your email later.
All listed fields are required.
By using our site, necessary cookies are set on your device for the execution of the service. Find out more in our data privacy policy
https://www.doka.com/data-privacy.
Thank you very much for your interest - Building Bigger Sewers to Accommodate Growth.
A link with further information has been sent to the provided e-mail address.
You can now switch back to the QR code reader to request information on other topics. You have the option to save your contact details to be automatically used for your next request.
Settings for cookies and third-party applications
Cookies and third-party applications are used on our website. This helps us to guarantee the best possible performance of our website, especially
the constant improvement of the functionality of our website (analysis of the user visit),
a smooth shopping experience when using the Doka online shop or
the placement of suitable advertising for users on certain platforms.
Do you consent to the use of cookies and the processing of personal data associated therewith?