calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkcartissuuclosekeystarweb
I consent to the use of cookies by this website for analyses and personalized content. Find out more OK
I consent to the use of cookies by this website for analyses and personalized content. Find out more OK

2nd Midtown Tunnel

United States of America

A new two-lane transportation tunnel under the Elizabeth River and parallel to the existing Midtown tunnel. This is the first SL-1 Tunnel project in the USA

Back

Project data

Year of completion
2018
Project duration
36 Months
Country
United States of America
Address
Norfolk and Portsmouth VA.
City
Portsmouth
Realization
Skanska-Kiewit-Weeks - Joint Venture
Structure
Tunnel
Type of structure
Cut-and-cover tunnel
Architect
Parsons Brinckerhoff

Floor-slab

Construction method
Arched
Cross-sectional shape
Multi-cell box girder – straight webs
Structure height
28,50 m
Number of spans
11
Longest span
54,00 m
Clear width
36,00 m
Clear height
21,50 m
Formed length of tunnel
3770 m
Shape
Radius
Type of carriage/traveller or formwork
Large formwork traveller
Number of casting sections
55
Cycle time
4 -day cycle
Form-tie pattern
Stipulated by architect
Type of edge
Rounded/chamfered edge