calldocumentfacebookmessagemypartnerwindowsapplegoogleplayworkerroutecoinspinterestplaysearchsmartphonetwittercaraccordeonvideoarrowarrowdownloaddownloaduploadsection_scrollerglobemapIcon-Shop-Websitecontactenergyhomebridgeshighrisetunnelmininghousearrow-uparrow-downarrow-leftarrow-leftarrow-circle-rightchevron-right-circleuserexternlinkclose
I consent to the use of cookies by this website for analyses and personalized content. Find out more OK
Contact
I consent to the use of cookies by this website for analyses and personalized content. Find out more OK

Formwork Solutions at the Meldahl Hydroelectric Project

01.08.2013 | Press
Featuring approximately 40,000 square feet of Doka’s pre-assembled Top 50 gang formwork, the Meldahl Project is designed to provide a new source of clean, zero emission electric generation for the national grid.

Impressions

  • 522 pre-assembled, conicalTop 50 gangs were delivered onsite.
  • Over 1 million pounds of Staxo was delivered and allowed for on-site pre-assembly for each level and segment.
Located on the Ohio River, approximately 40 miles east of Cincinnati at Foster, Kentucky, the Meldahl Project includes a 105 megawatt "run-of-the-river" hydroelectric plant. The challenge was to deliver this monumental project efficiently on an aggressive three-month schedule. As such, Doka was hired by Baker Concrete Construction to meet the challenge.

Design

The project design called for three, horizontal draft tubes with a conical shape starting with an approximate diameter of 36’-6” and transitioning into a rectangle at 59’ x 54’, with a total length of 91’-9”. Doka combined the efforts of their Chicago and Baltimore branches to meet these close tolerances and ensure the project was completed on time. Construction of the draft tubes began using Top 50 Formwork, a loose form system constructed from standard parts that can be assembled in any configuration for a wide range of applications. To allow for concrete to be placed faster, (522) pre-assembled, conical Top 50 gangs were delivered onsite and ready for immediate installation.

Pre-assembly

All Top 50 gang formwork that form the interior conical shape of the draft tubes were built and preassembled at Doka’s facility in Channahon, IL.

Doka’s experienced staff and state of the art carpentry shop worked day and night to construct all 522 individual gangs. Since each gang had a specific shape and location within the tube, all were individually numbered and shipped according to its pour ID number to provide maximum efficiency at the jobsite.

A grill of walers and beams was first dimensioned and assembled for each gang, then, the CNC machine shaping timbers were constructed to precise dimensions and attached to each grill along with a plywood form face. Next, the gang was labeled and the plywood face was covered with plastic for storage in Doka’s yard to provide quality and just-in-time delivery at the jobsite.

Load-bearing Tower Staxo 100

Doka’s Staxo 100 shoring was installed prior to the roof formwork assembly. This high performance, load-bearing tower is quick and easy to assemble and can be completed in a variety of ways to fit a wide range of field conditions. In addition, the flexibility of the system allows for maximum optimization of equipment and a reduction in necessary material. One million pounds of Staxo 100 Shoring was delivered and allowed for onsite pre-assembly for each level and segment.

"Staxo shoring is the safest system that I have ever used. The built in ladder, tie-offs and horizontal cross bracing make it a good system," said Kirt Inscho, superintendent, Baker Concrete Construction.

Staying on Schedule

To meet the demanding construction schedule, nearly 80 truckloads of Top 50 and Staxo 100 were delivered in total. To ensure safety on the jobsite, Doka’s field service was provided to educate and assist the crew on proper assembly of both Top 50 and Staxo 100.

"Doka's on-site field support was important to the success of this project,” said Inscho.

According to Michael Schaeffer, National Sales Manager, Doka’s experience on the Cannelton Hydroelectric Project assisted in the success of this project.

The Meldahl Project represents a significant economic development investment for the local community. More than 400 construction jobs were created for a variety of trade workers. The project is slated for commercial operation in 2014.

This could also be of interest for you:

Working with Formwork: Are you Safe?

04/17/2018 | Press

More than double your return on jobsite safety investments

04/17/2018 | News

Do you have any questions on the article? Get in touch with us!

Fields marked with * are required.
* Please fill out all required fields!
Message could not be sent – please try again a little later!
Many thanks for the enquiry!

We will get back to you as soon as possible.